Recent progress at the Uranium Processing Facility can be clearly seen now that the Mechanical Electrical Building is enclosed, structural steel is up at the Salvage and Accountability Building, and concrete placements continue for vertical walls at the Main Process Building.

Recent progress at the Uranium Processing Facility can be clearly seen now that the Mechanical Electrical Building is enclosed, structural steel is up at the Salvage and Accountability Building, and concrete placements continue for vertical walls at the Main Process Building.
Tags

yph-19-834049

Now that the first vertical wall has been placed at the Main Process Building, additional forms are added on to the inside and outside of the rebar wall curtain to prepare for the next concrete placements.

Now that the first vertical wall has been placed at the Main Process Building, additional forms are added on to the inside and outside of the rebar wall curtain to prepare for the next concrete placements.