UPF

UPF Milestones

2019 has been a big year at the Uranium Processing Facility (UPF). The UPF team had a busy summer and celebrated several milestone achievements. See a recap in this milestone compilation video.

YPH-19-850598

Progress continues at the Uranium Processing Facility. First floor structural steel installation is complete at the Salvage and Accountability Building; subcontractors and craft employees are busy with fireproofing and HVAC support and ductwork installation at the Mechanical Electrical Building; and first floor outer walls at the Main Process Building are complete while structural steel installation continues.

Progress continues at the Uranium Processing Facility. First floor structural steel installation is complete at the Salvage and Accountability Building; subcontractors and craft employees are busy with fireproofing and HVAC support and ductwork installation at the Mechanical Electrical Building; and first floor outer walls at the Main Process Building are complete while structural steel installation continues.
Tags: 

yph-19-840850

Forms are installed on the outside of a rebar wall curtain at the Main Process Building (MPB). Once inside and outside forms are installed, concrete is placed to construct the outside wall of the MPB.

Forms are installed on the outside of a rebar wall curtain at the Main Process Building (MPB). Once inside and outside forms are installed, concrete is placed to construct the outside wall of the MPB.
Tags: 

Pages