UPF

yph-19-836051

The Mechanical Electrical Building (MEB) at the Uranium Processing Facility is now fully enclosed. This milestone includes installation of all siding, doors, roof, and louvers, and completion of underground utility work on the east and north side of the MEB.

The Mechanical Electrical Building (MEB) at the Uranium Processing Facility is now fully enclosed. This milestone includes installation of all siding, doors, roof, and louvers, and completion of underground utility work on the east and north side of the MEB.
Tags: 

yph-19-832706

Now that the Mechanical Electrical Building is fully enclosed, work continues inside to prepare for miscellaneous steel installation; electrical installation; heating, ventilation, and air conditioning placement; fire protection; fire proofing and bulk commodity installations.

Now that the Mechanical Electrical Building is fully enclosed, work continues inside to prepare for miscellaneous steel installation; electrical installation; heating, ventilation, and air conditioning placement; fire protection; fire proofing and bulk commodity installations.
Tags: 

yph-19-836468

Cement finishers smooth out part of a 885 cubic yard concrete placement at the Salvage and Accountability Building (SAB). It was the final topping slab placement for the SAB.

Cement finishers smooth out part of a 885 cubic yard concrete placement at the Salvage and Accountability Building (SAB). It was the final topping slab placement for the SAB.
Tags: 

yph-19-836441

The first pieces of structural steel were installed at the Uranium Processing Facility Project’s Salvage and Accountability Building. The first phase of structural steel installation will continue over the summer and calls for almost 800 pieces that collectively weigh about 1,500 tons.

The first pieces of structural steel were installed at the Uranium Processing Facility Project’s Salvage and Accountability Building. The first phase of structural steel installation will continue over the summer and calls for almost 800 pieces that collectively weigh about 1,500 tons.
Tags: 

yph-19-836440

Recent progress at the Uranium Processing Facility can be clearly seen now that the Mechanical Electrical Building is enclosed, structural steel is up at the Salvage and Accountability Building, and concrete placements continue for vertical walls at the Main Process Building.

Recent progress at the Uranium Processing Facility can be clearly seen now that the Mechanical Electrical Building is enclosed, structural steel is up at the Salvage and Accountability Building, and concrete placements continue for vertical walls at the Main Process Building.
Tags: 

yph-19-836057

The final topping slab has been placed for the Salvage and Accountability Building. This was the last topping slab placement for the Uranium Processing Facility project.

The final topping slab has been placed for the Salvage and Accountability Building. This was the last topping slab placement for the Uranium Processing Facility project.
Tags: 

Pages