NNSA Administrator Lisa E. Gordon-Hagerty (center) with UPF Iron Workers in the Main Process Building
NNSA Administrator Lisa E. Gordon-Hagerty (center) with UPF Iron Workers in the Main Process Building
NNSA Administrator Lisa E. Gordon-Hagerty with UPF Iron Workers in the Main Process Building
NNSA Administrator Lisa E. Gordon-Hagerty studies a rendering at the UPF Salvage and Accountability Building
The UPF Project completed 12 Main Process Building (MPB) Concrete Wall Placements in just two months
Salvage and Accountability Building (SAB) completed its last concrete placement for elevated decks in June 2020
The UPF Project recognizes Lynch Bus Lines, a local school bus contractor, for their assistance during COVID-19 operations
Process Support Facilities (PSF) completed all piles and begin final excavation and mud mat placements
The Mechanical Electrical Building (MEB) continues to work through final construction activities to support turn-over to start-up in July and August
The Uranium Processing Facility Project Site in June 2020
Newly installed switchgear in the Mechanical Electrical Building (MEB)