The Uranium Processing Facility project completed the Site Infrastructure and Services subproject, which included completion of a concrete batch plant and a 65,000-square-foot Construction Support Building.The Uranium Processing Facility project completed the Site Infrastructure and Services subproject, which included completion of a concrete batch plant and a 65,000-square-foot Construction Support Building.

The Uranium Processing Facility project continues to make progress with the recent completion of the Site Infrastructure and Services subproject.

“Completing the SIS subproject is an important step in paving the way for future subprojects and to ultimately deliver UPF,” said UPF Federal Project Director Dale Christenson.

SIS is the second of seven subprojects that will construct UPF. Work included the completion of a concrete batch plant and a 65,000-square-foot Construction Support Building. There also was building demolition, utility work, site grading and installation of new erosion protection and security features as part of the SIS subproject.

Read the recent NNSA news release and watch this time-lapse video showing some of the current work.