Progress continues at the Uranium Processing Facility. First floor structural steel installation is complete at the Salvage and Accountability Building; subcontractors and craft employees are busy with fireproofing and HVAC support and ductwork installation at the Mechanical Electrical Building; and first floor outer walls at the Main Process Building are complete while structural steel installation continues.

YPH-19-850598
Tags: 

yph-19-840850

Forms are installed on the outside of a rebar wall curtain at the Main Process Building (MPB). Once inside and outside forms are installed, concrete is placed to construct the outside wall of the MPB.

Forms are installed on the outside of a rebar wall curtain at the Main Process Building (MPB). Once inside and outside forms are installed, concrete is placed to construct the outside wall of the MPB.
Tags: 

yph-19-841572

The Uranium Processing Facility Project team has completed the first four Main Process Building walls and all the 27-foot elevation rebar curtain walls have been erected.

The Uranium Processing Facility Project team has completed the first four Main Process Building walls and all the 27-foot elevation rebar curtain walls have been erected.
Tags: 

yph-19-839326

One of two capacitor banks for the Pine Ridge Substation is inspected during a turnover walkdown. The capacitor bank is designed to maintain a stable power supply for the Uranium Processing Facility and the Y-12 National Security Complex.

One of two capacitor banks for the Pine Ridge Substation is inspected during a turnover walkdown. The capacitor bank is designed to maintain a stable power supply for the Uranium Processing Facility and the Y-12 National Security Complex.