UPF

YPH-19-819752

Ironworkers began installing first-level rebar curtain Feb. 4 on the Main Process Building (MPB). The outside rebar layer will be joined by an inside layer for the exterior wall of MPB. Formwork will then be placed outside the curtain and the concrete placed.

Ironworkers began installing first-level rebar curtain Feb. 4 on the Main Process Building (MPB). The outside rebar layer will be joined by an inside layer for the exterior wall of MPB. Formwork will then be placed outside the curtain and the concrete placed.
Tags: 

YPH-19-819760

The last piece of structural steel was placed on the Mechanical Electrical Building on Feb. 11. The roof and the panels that make up the walls will be installed next. Completion is scheduled for early summer.

The last piece of structural steel was placed on the Mechanical Electrical Building on Feb. 11. The roof and the panels that make up the walls will be installed next. Completion is scheduled for early summer.
Tags: 

YPH-19-819893

Nearly 24,000 cubic yards of concrete were placed for the slab of the Main Process Building, UPF’s largest facility. Concrete placement for the slab was completed on Feb. 16.

Nearly 24,000 cubic yards of concrete were placed for the slab of the Main Process Building, UPF’s largest facility. Concrete placement for the slab was completed on Feb. 16.
Tags: 

Pages