YPH-22-1030902
Mechanical Electrical Building chilled water system
Mechanical Electrical Building chilled water system
Main Process Building Tool Prep Station table installation
Installation of a fire protection sprinkler main in the Salvage and Accountability Building
Installation of the Mechanical Electrical Building Power Monitoring and Control System Antenna Surge Protector
Pipefitters working tie-ins to the Salvage and Accountability Building POG Scrubber
Carpenters working on the HEUMF Connector
Mechanical Electrical Building electrical testing
Main Process Building equipment installation
Main Process Building siding installation
UPF Construction Site mid-June 2022