Y-12 Blog

Posted: Tuesday, October 19, 2021 - 4:43pm

Uranium Processing Facility's Main Process Building
The east side of the Uranium Processing Facility's Main Process Building

The Uranium Processing Facility (UPF) at the Y-12 National Security Complex successfully completed all third-level walls and concrete roof placements for the Main Process Building (MPB) on Wednesday, September 29, marking a major milestone for the UPF Project. This signifies the completion of structural construction for the MPB.

Construction work on the MPB began in 2018, and the interior construction and commissioning will be completed by the end of 2025. The MPB is one of seven UPF subprojects and the largest single building on the project. The 242,000-square-foot structure was built to nuclear construction standards, once completed and fully operational, will house casting, special oxide, and some chemical recovery processes.

The MPB subproject includes the construction and installation of the building as well as site preparation, long-lead procurements, the installation of the Perimeter Instruction Detection Assessment System (PIDAS), and a connector to the Highly Enriched Uranium Materials Facility (HEUMF).

“This milestone marks a major shift for our construction team on the UPF project,” said Dale Christenson, UPF Federal Project Director. “UPF construction team demonstrated the teamwork and tenacity necessary to complete the MPB structure working through the challenges that East Tennessee weather brings, and allows a majority of the work to be performed indoors.”

Construction will continue on the interior of the building as crews install key process modules, gloveboxes, and additional process equipment throughout the next few years. The remaining interior construction also includes additional work for subcontractors on heating and ventilation ductwork, fire protection piping, and interior finishes.

“Completing the structure for the MPB is a major achievement for the project as we continue to build our nation’s UPF,” said Dena Volovar, UPF Project Director. “We are moving the project forward, and we recognize it is vital to get the job done right. We have the right team to deliver UPF, and this achievement shows the great work that is being done each and every day.”

UPF supports the nation’s Uranium Mission Strategy, which ensures the long-term viability, safety, and security of enriched uranium capabilities in the United States. UPF will replace casting, special oxide production, and salvage and accountability capabilities from a World War II-era building with a modern and more efficient facility for conducting highly enriched uranium processing operations at Y-12 National Security Complex.

Dena Volovar, UPF Project Director
Dena Volovar, UPF Project Director speaks to craft personnel at the Main Process Building Civil Structure Completion Ceremony
From Left to Right: Mike Robinson, Bechtel UPF Project Manager;  Dale Christenson, UPF Federal Project Director; Dena Volovar, UPF Project Director; John Howanitz, President of Bechtel NS&E GBU; Gene Sievers, Y-12 Site Manager; and Jim Sowers, MPB Area Manager
From Left to Right: Mike Robinson, Bechtel UPF Project Manager; Dale Christenson, UPF Federal Project Director; Dena Volovar, UPF Project Director; John Howanitz, President of Bechtel NS&E GBU; Gene Sievers, Y-12 Site Manager; and Jim Sowers, MPB Area Manager
Tags:
Posted: Friday, September 17, 2021 - 11:37am

LiveWise mural
This LiveWise mural brands the renovated fitness centers and makes the centers easily recognizable.

Some rejuvenating reps have the East and West LIFE Centers at Y-12 looking pretty buff.

The 11-year old structures have received makeovers. They now boast fresh paint, power washed and replaced trim, and new eye catching murals. Inside the West site, bathrooms sport new flooring, and ceiling tiles have been replaced.

“We’re excited to present the updated facilities,” said Consolidated Nuclear Security’s Health and Wellness Supervisor Karen Lacey. “They are a real value to employees. This helps set the tone for the importance we place on wellness and the health of our people, the most important resource.”

The centers have two different color schemes. East is cream with gray trim, while West is also cream but with red accents. They provide a backdrop for two of Lacey’s favorite additions, the LiveWise murals.

“Now it’s branded,” she said. “The logo makes them easily recognizable, easily distinguishable. People now know that it is part of the LiveWise Program.”

The renovations have been in the making for some time.

“It’s been 3 years trying to put this together,” Lacey said. “It started coming together in the spring, when we were able to get funding.”

The East and West centers are smaller offshoots of the larger fitness facility at Jack Case Center. They feature cardio and strength equipment, and change houses are next door. Like the JCC location, both are open 24 hours, 7 days a week. The centers have more than 4,000 usages each month.

In addition to the fitness equipment, there are LiveWise classes, such as outdoor boot camp sessions and virtual yoga. New to the roster is functional fitness training, which offers workouts in a small group setting. It focuses on exercises that train muscles to work together and prepares them for daily tasks by simulating common movements done at home, work, or in sports.

“I think this will attract some new people to the center,” Lacey said. “It’s a little less intimidating than taking a class with a lot of people.”

LiveWise also offers discounted (or free) registration to sports events, mobile mammography, and other health education programming.

“We’re as good as any gym in the community,” Lacey said, “and it’s always free. We’ve just saved employees 30 bucks a month.”

Members of the crew that made the upgrades possible
Members of the crew that made the upgrades possible gather at the East LIFE Center

Tags:
Posted: Thursday, September 16, 2021 - 3:33pm

Thanks to the CNS General Workplace Improvement Program, the Pantex and Y-12 sites have received several upgrades.

Thanks to the CNS General Workplace Improvement Program, the Pantex and Y-12 sites have received several upgrades.

Investments have been made to revitalize aging infrastructure at both sites. The CNS General Workplace Improvement Program, which annually identifies, prioritizes, and executes projects in common areas to better quality of life for employees, has been working on several upgrades.

At Pantex, improvements underway range from new digs for guards to a fix that’s sure to be a bright spot.

The installation of a new guardhouse is set to be completed in September at the Building 16-19 portal entry.

“The existing one is somewhat small and cramped,” said Program Manager Todd Clark. “The new one is probably double the space. This will be a bigger building to more comfortably house personnel and equipment.”

Clark is also overseeing installation of windbreaks at the east and west entry portals. The aluminum alloy booths are heated and will offer protection from extreme wind and cold weather conditions at the posts. They will be used by guards when weather conditions warrant and morning portal activity is high, Clark said. Construction has already started at the west gate. Projected completion is September 30.

Solar lights have been placed at crosswalks and provide a brighter path for Pantexans traveling from an overflow parking lot.
Solar lights have been placed at crosswalks and provide a brighter path for Pantexans traveling from an overflow parking lot.

Another project makes the Building 12-70 parking lot brighter and safer. Solar lights have been installed by construction and maintenance crews at two crosswalks, which workers use to travel from an unlit overflow parking lot.

“Employees must cross the road at two points to access the plant,” Clark said. “The crossing is a potential safety hazard in low lighting conditions. The lights will create safer conditions and better visibility for employees.” Construction was completed in July.

While these projects focus on outdoor changes, other improvements at Pantex tackle interiors.

In one building, four restrooms are slated to be remodeled by September. The renovations include new floors, toilets, urinals, partitions, sinks, exhaust fans, fresh paint, and improved heating and cooling capabilities.

Program Manager Dustin Broom said, “Personnel will have adequate restrooms and a conducive work environment that improves quality of life.”

Also, office area modifications are in the works at another building. Among the changes are new flooring, paint, ceiling tiles and roof, electrical configuration, and a conference room system for improved meeting and videoconferencing capabilities.

“This refurbishment will improve employee habitability and provide adequate office space for personnel,” Broom said.

Y-12 has made an effort to create a better environment for employees as well.

“Workplace improvements are essential to the current and future of the Y-12 site,” said Program Manager Chad Kitts. “The Maintenance and Repair Program strives to complete General Workplace Improvement projects each year to improve quality of life for the Y-12 workforce.”

At Building 9212, outdated flooring in the office and cubicle areas has been replaced with overlay flooring; a base has been installed, which will facilitate easier cleaning and more sanitary conditions. “The effort updated the facility’s habitability to today’s standard,” Kitts said. Also, the walls in the mezzanine men’s restroom in Building 9204-02 received a paint job.

A crane replacement will deliver safer work conditions at Building 9215. The machine includes a hoist with a wireless remote control. This improvement removes workers from exposure to the molten salt bath. The planning phase is completed, and the execution phase is in progress. This project is slated to be finished by February 2022.

A roof access staircase at Y-12’s Building 9720-05 makes maintenance and surveillance safer for workers..
A roof access staircase at Y-12’s Building 9720-05 makes maintenance and surveillance safer for workers.

Steps in the right direction have been taken at Building 9720-05. A roof-access staircase was installed June 2020. It allows safe access to the roof and enables workers to efficiently complete surveillance and maintenance activities.

“The staircase provides maintenance personnel and other employees with safer and easier access to rooftop equipment,” said Program Manager Beverly Ward. “We have also eliminated the cost associated with erecting and removing temporary access and fall protection.”

Other projects are in various stages of planning and funding, so more workplace improvements will be implemented at Pantex and Y-12 in the months ahead.

Posted: Thursday, September 16, 2021 - 2:56pm

Program Management University graduates

In this photo from 2019, a group of Program Management University graduates gather to celebrate the end of their sessions. Now, most of the classes are virtual with in person sessions once travel restrictions are relaxed.

Managing an NNSA program involves a lot of moving parts. To be successful, program managers need to juggle a host of skills — planning, budgeting, evaluating, managing, and integrating multiple, complex project initiatives, priorities, and transitions, often over long periods of time. These are the skills Pantex and Y-12 program managers are mastering through Program Management University.

What is PMU?
Developed for interested Pantex, Y-12, and NNSA Production Office employees, PMU has held classes every year since 2018. As of early 2021, more than 200 staff members across a variety of site organizations have either completed or are attending the training. Upcoming sessions are scheduled for later this year and again in 2022.

PMU is a thoughtfully constructed and continuously evolving curriculum with several objectives that promote performance improvement in program management and critical interfaces, while informing and calibrating attendees to a set of clear expectations,” said David Young, NPO assistant manager for Programs and Projects.

What makes PMU unique?
The training enables consistent and uniform management of programs across Pantex and Y-12. Some programs, such as Stockpile Programs, also require new managers to have more technical qualifications tailored to managing specific requirements and interacting with design agencies.

“The goal of PMU is to achieve ‘best in class’ program management across the Nuclear Security Enterprise by providing NNSA with consistently superior management of all programs,” said Dan Linehan, senior director of Mission Baseline and Indirect and Technology Programs. “PMU enhances a program manager’s understanding of the broader NNSA mission and augments communications across Pantex and Y-12.”

What are the benefits of PMU training?
“I am new to the Program Integration organization and recently completed the PMU curriculum,” said Marina Yeary, director of Technology Development and Transfer for Program Integration. “The range of information covered is impressive, including NNSA directives, Pantex and Y-12 missions, Program Integration business processes, and program manager skills and qualifications. The training has enhanced my understanding of my role, the business, our customer, and our goals.”

PMU consists of three, one week sessions where the first session is an overview of the Nuclear Security Enterprise and NNSA’s programs. The second is a review of tools and techniques, and the third focuses on skills development.

The class content has been refined over time and now includes virtual classes. The second session will be held virtually while the first and third sessions will be held at Pantex and Y-12 to allow for in person interaction and tours once travel restrictions are relaxed.

“During each training session, quizzes are taken along with a final exam,” Linehan said. “Ongoing success is measured by how well our customer perceives each program’s performance. Finally, because program managers are more effective and efficient at managing their programs after attending PMU, we are seeing validated cost savings.”

Posted: Wednesday, September 15, 2021 - 4:53pm

Congratulating Bechtel Global Scholars

Congratulations to the Bechtel Global Scholars with ties to Pantex, Y 12, and the Uranium Processing Facility.

The 2021 Bechtel Global Scholars program awarded a total of $75,000 in college funds to 25 students in six countries. The $3,000 scholarship goes to students in their first year of studies at an accredited college, university, vocational institute, or technical school.

Among the 25 students receiving the scholarship this year, five are a child of a Consolidated Nuclear Security or Uranium Processing Facility Project employee:

  • Jocelyn Espinoza, daughter of Pantex’s Andrew Espinoza
  • Olivia Horner, daughter of Pantex’s Robbie White
  • Nathan Nelson, son of UPF’s Jeanne Grozdanich Nelson
  • Alexandria Perry, daughter of Y 12’s Douglas Perry
  • Oviya Shanmugam, daughter of UPF’s Nambi Shanmugam

Oviya Shanmugam thanked Bechtel for the opportunity. “I consider it a great honor to have been chosen as a recipient of this scholarship,” she said.

Her father, Nambi Shanmugam, said, “I appreciate Bechtel for identifying, recognizing, and rewarding young achievers on their first step toward higher education. It is especially encouraging after overcoming a very challenging last year.”

Parent Robbie White also expressed his appreciation to Bechtel. “We feel honored for the selection and thankful for the aid during this transition year as our youngest daughter leaves the nest,” he said.

Jocelyn Espinoza said the scholarship will help further her education. “I am very excited to have been selected for this award, and it will go a long way to help me achieve my goals,” she said.

Bechtel Group Foundation funds the scholarship, which is managed by Scholarship America, a nonprofit organization dedicated to encouraging global educational achievement. This year, 160 students from eight countries applied for the scholarship. Scholarship America reviewed each application before the final selection.

The opportunity is open to students in all fields of study, with preference given to those pursuing degrees in science, technology, engineering, or math. Bechtel scholarships are awarded each year for full-time study at an accredited institution of the student’s choice. However, current undergraduates are not eligible for the program.

Since its start in 2001, the Bechtel Global Scholars program has awarded $1.3 million in college funding to 486 students.

Quotes from the scholars
Jocelyn Espinoza: “I am very excited to have been selected for this award, and it will go a long way to help me achieve my goals.”

Olivia Horner: “I’m very thankful for this investment in my future. I am very thankful for the recognition of my hard work throughout high school. I am incredibly excited to pursue my business degree at Texas A&M University!”

Nathan Nelson: “My family and I are both grateful to be considered and awarded this scholastic opportunity to help further my education. Thank you very much!”

Alexandria Perry: “It is an honor to be chosen to represent my high school and my family in accepting this generous scholarship. I feel a remarkable amount of support and personal enthusiasm as I begin my collegiate journey, and I am very thankful!”

Oviya Shanmugam: “I am thankful to Bechtel for the opportunity and consider it a great honor to have been chosen as a recipient of this scholarship. This award will be a great addition to support my college tuition.”

Pages